← Opportunities

Cross Island Parkway (US 278) Toll Conversion Design-Build Project

Funder
South Carolina Department of Transportation · SCDOT Design-Build Program ⚪ No history
Type / status
rfp · open
Amount
—
Deadline
unknown
“These steps will follow the Milestone Schedule in Section 8. SCDOT reserves the right to make changes to the above steps and Milestone Schedule as appropriate to meet the needs of the procurement process.”
Ecosystems
Categories
infra
Tech stack
Apply
https://www.scdot.org/business/cross-island-parkway-us278.aspx
Source
https://www.scdot.org/content/dam/scdot-legacy/business/pdf/cross-island-parkway/Request%20for%20Proposals%20(Final%20with%20Revisions%20Highlighted).pdf
Fit
8% · poor fit · The team's expertise in ZK, privacy, and Rust/Leo is entirely unrelated to a highway toll plaza removal and roadway reconstruction project.
Trust
75% · model self-report 75% · first seen 2026-10-26 · v1
Verified
2026-11-17 · page says open: "the opportunity by South Carolina Department of Transportation (SCDOT) to submit a Proposal in response to this RFP. Partnerships, corporations, Limited Liability Companies"

The South Carolina Department of Transportation (SCDOT) is seeking proposals from short-listed design-build teams to remove the existing toll plaza, reconstruct pavement, and realign roadway on the Cross Island Parkway (US 278) in Beaufort County. The project aims for cost and schedule certainty, expedited toll infrastructure removal, and minimal traffic impacts. Interested short-listed proposers must submit technical and cost proposals per the milestone schedule.

Eligibility: Open only to short-listed proposers identified in Phase 1 of the two-phased selection process. Proposers must be firms, consortia, partnerships, LLCs, sole proprietorships, joint ventures, or other legal entities.

Pipeline

Override status:

Funder track record · does South Carolina Department of Transportation actually pay grants?

⚪ No payout history found · checked 2026-10-26 · 0 forum reports, 10 web pages read

Proven payer: at least 3 named grantees and one payout in the last 90 days. Every grantee below is quoted word for word from its source. When a source does not date a grant, the date is when that page or post was published.

Trust breakdown (2/2 checkable facts verified)

SignalWeightResultNote
apply link0.075100%link in source
funder0.075100%named in source
source quality0.1550%social or search hit
model confidence0.175%model self-report

Fit breakdown (against the ORG_* profile)

SignalWeightResultNote
model fit0.510%model rated 10%
ecosystem overlap0.250%none vs aleo
category overlap0.1517%infra vs zk, privacy, infra, dev_tooling, security, interoperability
tech overlap0.10%none vs rust, leo, zk

Sources (1)

RoleDocumentFromFetched
primaryRequest for Proposals (Final with Revisions Highlighted)Web discovery: ecosystem sweep2026-10-26

History (1)

vChangedFields
12026-10-26created

Extracted text

Cross Island Parkway (US 278)
Toll Conversion
Design-Build Project
Project ID P040119
Beaufort County
September 13, 2021
Request for Proposals

Project ID P040119 SCDOT | Design-Build Project Page 1
Cross Island Parkway (US 278) Toll Conversion
Beaufort County, South Carolina
Cross Island Parkway (US 278) Toll Conversion
Beaufort County, South Carolina
A Design-Build Project
Project ID P040119
REQUEST FOR PROPOSALS (RFP) INDEX
Request for Proposals Instructions
Attachment A: Agreement
Exhibit 1. Cost Proposal Bid Form
Exhibit 2. Schedule of Values
Exhibit 3. Scope of Work
Exhibit 4. Project Design Criteria
4a. Roadway Design Criteria
4b. Structures Design Criteria
4c. Pavement Design Criteria
4d. Traffic Design Criteria
Part 1 – Signing and Pavement Markings
Part 2 – Work Zone Traffic Control
4e. Hydraulic Design Criteria
4f. Geotechnical Design Criteria
4z. Project Design Deliverables
Exhibit 5. Special Provisions and Contract Requirements
Exhibit 6. Environmental Criteria
Attachment B: Supplemental Project Design Criteria
Project Information Package

REQUEST FOR PROPOSALS
INSTRUCTIONS

Project ID P040119 SCDOT | Design-Build Project Page 1 of 2
Cross Island Parkway (US 278) Toll Conversion
Beaufort County, South Carolina
TABLE OF CONTENTS
PURPOSE OF REQUEST FOR PROPOSALS .......................................................................................1
PROJECT OVERVIEW.....................................................................................................................1
2.1 PROJECT DESCRIPTION .......................................................................................................................... 1
2.2 PROJECT GOALS ................................................................................................................................... 1
2.3 PROJECT INFORMATION ......................................................................................................................... 2
2.4 SCDOT POINT OF CONTACT................................................................................................................... 2
2.5 RFP COMMITTAL ................................................................................................................................. 3
2.6 NEPA DOCUMENT/PERMIT ................................................................................................................... 3
2.7 SCHEDULE ........................................................................................................................................... 3
GENERAL INSTRUCTIONS ..............................................................................................................3
3.1 DESIGN-BUILD SELECTION METHOD ........................................................................................................ 3
3.2 RFP FOR INDUSTRY REVIEW ................................................................................................................... 4
3.3 NON-CONFIDENTIAL QUESTIONS, CLARIFICATIONS, AND OPEN-FORUM MEETING .......................................... 5
3.4 FINAL RFP........................................................................................................................................... 5
3.5 ADDITIONAL NON-CONFIDENTIAL QUESTIONS, CLARIFICATIONS AND OPEN-FORUM MEETINGS......................... 5
3.6 CONFIDENTIAL QUESTIONS..................................................................................................................... 6
3.7 PRELIMINARY ALTERNATIVE TECHNICAL CONCEPTS .................................................................................... 7
3.8 FORMAL ALTERNATIVE TECHNICAL CONCEPTS ........................................................................................... 9
3.9 CONFIDENTIALITY ............................................................................................................................... 14
3.10 STIPENDS ................................................................................................................................ 14
3.11 CHANGES IN PROPOSER’S ORGANIZATION; KEY INDIVIDUALS ........................................................... 14
3.12 ORGANIZATIONAL CONFLICTS OF INTEREST; PROHIBITED COMMUNICATIONS; RESTRICTED PERSONS ...... 15
PROPOSAL DEVELOPMENT AND SUBMITTAL...............................................................................16
4.1 TECHNICAL PROPOSAL ......................................................................................................................... 16
4.2 COST PROPOSAL ................................................................................................................................. 20
4.3 PROPOSAL SUBMITTAL ........................................................................................................................ 21
4.4 CONFIDENTIALITY OF PROPOSALS .......................................................................................................... 22
4.5 NON-COLLUSION AND EQUAL EMPLOYMENT OPPORTUNITY CERTIFICATION ................................................. 22
EVALUATION OF PROPOSALS......................................................................................................23
5.1 EVALUATION COMMITTEE .................................................................................................................... 23
5.2 PROPOSAL REVIEW ............................................................................................................................. 23
5.3 TECHNICAL PROPOSAL EVALUATION ...................................................................................................... 23
5.4 PRESENTATIONS ................................................................................................................................. 24
5.5 CLARIFICATIONS ................................................................................................................................. 25
5.6 COMMUNICATIONS ............................................................................................................................. 25
5.7 TECHNICAL AND COST PROPOSAL ANALYSIS ............................................................................................ 26
5.8 WEIGHTED CRITERIA DETERMINATION ................................................................................................... 27
5.9 DISCUSSIONS ..................................................................................................................................... 28
5.10 BEST AND FINAL OFFER.............................................................................................................. 29
5.11 PROTEST ................................................................................................................................. 29

Project ID P040119 SCDOT | Design-Build Project Page 2 of 2
Cross Island Parkway (US 278) Toll Conversion
Beaufort County, South Carolina
SELECTION OF CONTRACTOR ......................................................................................................31
GENERAL INFORMATION ............................................................................................................31
7.1 RESERVED RIGHTS .............................................................................................................................. 31
7.2 OTHER GENERAL TERMS: ..................................................................................................................... 32
MILESTONE SCHEDULE ..............................................................................................................35
COST PROPOSAL BID FORM ........................................................................................................36
NON-COLLUSION CERTIFICATION................................................................................................38
EQUAL EMPLOYMENT OPPORTUNITY CERTIFICATION .................................................................39
STIPEND ACKNOWLEDGEMENT FORM ........................................................................................40
STIPEND AGREEMENT ................................................................................................................41
BID BOND FORM ........................................................................................................................44

Project ID P040119 SCDOT | Design-Build Project Page 1 of 44
Cross Island Parkway (US 278) Toll Conversion
Beaufort County, South Carolina
PURPOSE OF REQUEST FOR PROPOSALS
The purpose of this Request for Proposals (RFP) is to select a Proposer to perform the Project
services and to design and construct the Project, as further described in this RFP. SCDOT
desires that this Project be designed and constructed in a very efficient and timely manner. The
proposed Project services are hereinafter referred to as the “Project”. “Proposer,” as used here,
includes a firm or firms, consortia, partnerships, Limited Liability Company, sole
proprietorship, joint ventures, and other legal entities that has been short-listed and provided
the opportunity by South Carolina Department of Transportation (SCDOT) to submit a
Proposal in response to this RFP. Partnerships, corporations, Limited Liability Companies
(LLC), joint ventures, or other joint entities are collectively referred to herein as joint ventures.
The Proposer shall become the Contractor if awarded the Contract.
It is not the intention of SCDOT to receive complete detailed Project analysis and design prior
to the selection of a Proposer and the later execution of the Contract. Rather, the response to
this RFP shall provide sufficient information to be evaluated by SCDOT to determine if the
Proposal is in accordance with the specified process and criteria. The Proposal shall be specific
enough on assumptions used in its preparation so as to provide the basis for finalizing the
Contract.
PROJECT OVERVIEW
2.1 Project Description
The toll on the Cross Island Parkway (US 278) in Beaufort County is set to expire in
2021. SCDOT proposes, at a minimum, to remove the existing toll plaza, including toll
canopy, booths, and excess pavement. In addition, the project will include pavement
reconstruction of mainline cross Island Parkway and interchange ramps along with the
roadway realignment between Marshland Road interchange and the bridge over Broad
Creek.
SCDOT intends to enter into a contract for services as detailed in the Contract and
Contract’s Exhibits. The Proposer shall be responsible for meeting all Project
requirements, specifications, and other applicable criteria as set forth in “Attachments A
and B”. Attachment B - Supplemental Project Design Criteria is located on the SCDOT
Design-Build website at https://www.scdot.org/business/cross-island-parkway-
us278.aspx.
2.2 Project Goals
It is the intent of SCDOT to achieve the following goals and objectives for this project.
• Cost and schedule certainty
• Expedited removal of tolling infrastructure
• Pavement strengthening
• Minimal impacts to traffic
• No change orders

Project ID P040119 SCDOT | Design-Build Project Page 2 of 44
Cross Island Parkway (US 278) Toll Conversion
Beaufort County, South Carolina
• No change to key individuals
2.3 Project Information
Project Information, containing electronic files applicable to the Project, is posted on the
SCDOT Design-Build website. The Project Information Package will include
information describing the work performed or obtained by SCDOT prior to entering into
the Contract. The Project Information Package may contain additional information not
provided at the RFQ stage. The Project Information Package, which is posted on the
SCDOT Design-Build website, is for information only and is not part of the Contract.
SCDOT makes no representations or warranties regarding the reliability or accuracy of
the information contained therein and Proposers assume the risk in using this
information. Any available existing roadway plans can be obtained from the SCDOT
Design-Build website at https://www.scdot.org/business/design-build.aspx. Any
available existing bridge plans will be provided to the short-listed Proposers via upload
to a secured ProjectWise folder.
Proposers are encouraged to review all available information in the Project Information
Package, visit the Project site, and make any additional subsurface explorations or soil
tests that the Proposer may desire for purposes of preparing the Proposal. Any
information contained in Project Information Package is for information only, is not part
of the contract and SCDOT makes no representation or warranties regarding such
information. The Proposer shall obtain any permits or permissions required prior to any
additional subsurface exploration. The Proposer shall obtain permission from any
landowner prior to entering private property. The Proposer shall obtain encroachment
permits for any investigations within the right of way.
2.4 SCDOT Point of Contact
Ms. Carmen Wright is the Primary point of contact (POC) and addressee for receiving
all communications about the Project with copies to Mr. Brian Gambrell, Alternate #1
POC, and Mr. Jae Mattox, Alternate #2 POC. The Alternate POCs have been identified
in the event of the unavailability of the Primary POC but are not intended to be substitutes
for the Primary POC. No contact is allowed with any SCDOT personnel concerning this
Project except for questions of an administrative nature or as expressly permitted under
this RFP, in either case that shall be submitted in writing to the attention of the Primary
SCDOT POC (email is acceptable) with a copy to the Alternate POCs. This restriction is
in effect until the earliest of Contract award, termination of this procurement, or such
other time as identified by SCDOT to the short-listed Proposers in writing. Any Proposer
engaging in prohibited communications may be disqualified at the sole discretion of
SCDOT. Written inquiries from the Proposer’s POC (as identified in the Proposer’s
SOQ) shall be sent to:
Mail Delivery: Ms. Carmen Wright
(Mr. Brian Gambrell, Mr. Jae Mattox)
Office of Project Delivery
(Office of Chief Counsel, Preconstruction Design-Build Group)

Project ID P040119 SCDOT | Design-Build Project Page 3 of 44
Cross Island Parkway (US 278) Toll Conversion
Beaufort County, South Carolina
South Carolina Department of Transportation
955 Park Street, Room Room 101 (Room 302, 421)
Columbia, South Carolina 29202-0191
E-mail: WrightCL@scdot.org
(GambrellBC@scdot.org, MattoxJH@scdot.org)
2.5 RFP Committal
The submittal of a Proposal in response to this RFP shall constitute the Proposer’s
agreement to enter into the Contract with SCDOT for the completion of the Project under
the terms set forth in the Contract, Contract Exhibits, attached hereto as “Attachment A”
and Supplemental Project Design Criteria, located on the SCDOT Design-Build website
as Attachment B.
2.6 NEPA Document/Permit
No NEPA document was required for this project.
It was determined that the jurisdictional waters/wetlands (waters of the US (WOUS))
may be present within the project study area but would be avoided during construction.
If impacts to WOUS cannot be avoided and a US Army Corps of Engineer’s 404 permit
is required, the Proposer shall complete all necessary work, environmental studies, and
document preparation in order to obtain the applicable permit.
The preparation of all other necessary permit applications will be the responsibility of
the Proposer. Regarding any permit or license that must be obtained in the name of
SCDOT, the Proposer shall perform all functions within its power to obtain the permit or
license, and SCDOT shall fully cooperate in this effort and perform any functions that
must be performed by SCDOT.
2.7 Schedule
Contract time requirements are included in Agreement Article IV. This project shall
require an Interim Condition as defined in Exhibit 3 Scope of Work. The Proposer shall
enter the Interim Condition “B” time on the Bid Form. Upon Contract Execution,
SCDOT will enter the winning Proposer’s Interim Condition time into the Agreement,
Article IV. The Interim Condition time shall not exceed 90 calendar days.
GENERAL INSTRUCTIONS
3.1 Design-Build Selection Method
For this Project, SCDOT chose the two-phased selection method. Phase 1, which
identified a short-list of qualified Proposers, is complete.
In Phase 2, SCDOT invites each of the short-listed Proposers to submit their Proposals
for completion of the Project. After evaluation of the Proposals, SCDOT plans to award

Project ID P040119 SCDOT | Design-Build Project Page 4 of 44
Cross Island Parkway (US 278) Toll Conversion
Beaufort County, South Carolina
and execute the Contract with a single Contractor. A general overview of Phase 2
includes, but is not limited to, the following steps:
SCDOT releases RFP for Industry Review
SCDOT holds Open-Forum Meeting with Proposers to clarify/revise RFP
SCDOT releases Final RFP
Proposers submit Preliminary Alternative Technical Concepts (ATC), Confidential
and Non-Confidential Questions
SCDOT conducts Confidential One-on-One Meetings with Proposers to discuss
Preliminary ATCs and Confidential Questions, if neccessary
SCDOT conducts Open-Forum Meetings with all Proposers, if necessary
Proposers submit Formal ATCs and any additional Confidential, and Non-
Confidential Questions
SCDOT conducts Confidential One-on-One Meetings with Proposers to discuss
Formal ATCs and additional Confidential Questions, if necessary
SCDOT conducts Open-Forum Meetings with all Proposers, if necessary
SCDOT approves/disapproves Formal ATCs
Proposers submit Proposals
SCDOT evaluates Proposals
SCDOT conducts Bid Opening, recommends , and selects a Contractor
These steps will follow the Milestone Schedule in Section 8. SCDOT reserves the right
to make changes to the above steps and Milestone Schedule as appropriate to meet the
needs of the procurement process. The following paragraphs provide information
detailing various steps of the procurement.
3.2 RFP for Industry Review
The intent of distributing the RFP for Industry Review to the short-listed Proposers is to
identify and resolve conflicts, errors, mistakes, and/or ambiguities in the RFP, as well as
review risk and commercial terms to ensure maximum competition, competitive pricing,
and ultimately Project completion.

Project ID P040119 SCDOT | Design-Build Project Page 5 of 44
Cross Island Parkway (US 278) Toll Conversion
Beaufort County, South Carolina
3.3 Non-Confidential Questions, Clarifications, and Open-Forum Meeting
Once the RFP for Industry Review is issued, the Proposers may submit non-confidential
questions and/or comments relating to the RFP. An Open-Forum Meeting with all
Proposers present will be held on the date provided in the Milestone Schedule to discuss
and edit the RFP for Industry Review. Non-confidential questions will be accepted via
electronic upload to ProjectWise on the dates provided in the Milestone Schedule.
Proposers shall submit their questions or comments using the Questions Submittal Form
which can be downloaded from the SCDOT Design-Build website under the SCDOT
Design-Build Standard Forms Section. Responses posed during the Open-Forum
Meeting will not be attributed to the submitting Proposer.
All Question Submittal Forms shall be named in accordance with the Design-Build File
Naming Conventions from the SCDOT Design-Build website under the Design-Build
Resources Section.
https://www.scdot.org/business/pdf/design-
build/DB_Projectwise_Naming_Conventions.pdf
SCDOT reserves the right to accept or reject non-confidential questions received after
the milestone deadline. SCDOT will review all questions and/or requests for clarification
and, in its sole discretion, may incorporate the responses in the Final RFP. Prior to the
Open-Forum Meeting, SCDOT will post on the SCDOT Design-Build website written
responses to the questions and request for clarifications received, without attribution to
the submitting Proposer. Any new questions or requests for clarification asked during
the Open-Forum Meeting shall be submitted to SCDOT in writing within 24 hours of the
meeting. SCDOT’s written responses to Proposers’ questions and request for
clarifications are for general information only, are non-binding, do not constitute legal or
other advice, are subject to change with succeeding questions, answers, or addendums,
do not amend or form part of the Final RFP, and SCDOT is under no obligation to address
responses in revisions to the Final RFP documents.
3.4 Final RFP
After completion of the Questions, Clarifications, and Open-Forum Meeting stage,
SCDOT may incorporate the Proposers’ comments into the RFP, and a Final RFP will
be issued. Items that are revised, inserted, or deleted will be highlighted in the Final RFP.
In addition to releasing a highlighted version of the Final RFP, SCDOT will also
concurrently release a clean version of the Final RFP where all revisions, insertions, and
deletions are not highlighted. It is this clean version of the Final RFP that will be utilized
if any future Addendums are required.
3.5 Additional Non-confidential Questions, Clarifications and Open-Forum Meetings
Once the Final RFP is issued, SCDOT will allow Proposers to submit additional non-
confidential questions or comments to point out mistakes or ambiguities in the RFP.

Project ID P040119 SCDOT | Design-Build Project Page 6 of 44
Cross Island Parkway (US 278) Toll Conversion
Beaufort County, South Carolina
SCDOT will review all non-confidential questions and/or requests for clarification and,
in its sole discretion, may incorporate the responses in the RFP through an Addendum.
SCDOT will respond in writing to the non-confidential questions and requests for
clarifications received. The written responses will be posted to the SCDOT Design-Build
website within 10 business days of the deadline for submittal of non-confidential
questions in the Milestone Schedule. If responses are provided, SCDOT may hold an
Open-Forum Meeting where all Proposers will be invited to attend. This meeting may
be conducted via conference call or other electronic means. A Proposers’ failure to attend
this meeting will not relieve the Proposer of the responsibility for estimating properly the
difficulty and cost of successfully performing the work, or for proceeding to successfully
perform the work without additional expense to SCDOT. SCDOT’s written responses to
Proposers’ questions and requests for clarifications are for general information only, are
non-binding, do not constitute legal or other advice, are subject to change with
succeeding questions, answers, or addendums, do not amend or form part of the Final
RFP, and SCDOT is under no obligation to address responses in revisions to the Final
RFP documents.
Non-confidential questions will be accepted via electronic upload to ProjectWise on the
dates provided in the Milestone Schedule. Written questions submitted outside of these
dates may not be accepted. If deemed necessary by SCDOT, Open-Forum Meetings will
be held within 10 business days of the non-confidential questions Milestone Schedule
deadline. Any new questions or requests for clarification asked during the Open-Forum
Meeting shall be submitted to SCDOT in writing within 24 hours of the meeting.
Proposers must use the Question Submittal Form that is provided on the SCDOT Design-
Build website under the SCDOT Design-Build Standard Forms Section.
https://www.scdot.org/business/design-build.aspx.
3.6 Confidential Questions
Once the Final RFP is issued, SCDOT will allow Proposers to submit confidential
questions to provide the Proposer an opportunity to confidentially discuss the contents of
its Proposal with SCDOT personnel. Confidential questions will be accepted via
electronic upload to ProjectWise on the dates identified in the Milestone Schedule.
Written questions submitted outside of these dates may not be accepted.
SCDOT will determine, in its sole discretion, if confidential questions submitted are
considered confidential. If submitted confidential questions are determined to be of non-
confidential nature or identify an error or omission in the RFP, SCDOT, if it deems
appropriate, in its sole discretion, may incorporate them in the RFP through an
Addendum. If submitted confidential questions are determined to be of non-confidential
nature or if non-confidential questions are asked during any confidential meeting,
SCDOT will not respond and the Proposer may resubmit in accordance with Section 3.5.
SCDOT will provide written responses to the submitted confidential questions prior to
the Confidential Preliminary ATC Meeting and/or any Confidential One-on-One Formal

Project ID P040119 SCDOT | Design-Build Project Page 7 of 44
Cross Island Parkway (US 278) Toll Conversion
Beaufort County, South Carolina
ATC Meetings. SCDOT’s written responses to Proposers’ questions are for general
information only, are non-binding, do not constitute legal or other advice, are subject to
change with succeeding questions, answers, or addendums, do not amend or form part of
the Final RFP, and SCDOT is under no obligation to address responses in revisions to
the Final RFP documents. Written responses to confidential questions raised during the
meeting may be provided if deemed necessary; however, such questions and responses
will be identified and narrowly tailored. No oral discussions during the Confidential
Preliminary ATC Meeting and/or any Confidential One-on-One Formal ATC Meetings
shall be binding on SCDOT.
Confidential questions received on the dates prior to the Confidential Preliminary ATC
Meetings with Proposers may be discussed at that meeting. For confidential questions
received on the allowable date(s) after the Confidential Preliminary ATC Meeting,
written responses will be provided prior to a Confidential One-on-One Questions
Meeting/conference call which may be held within 10 business days following receipt of
the confidential questions or as determined necessary by the SCDOT POC. Proposers
must use the Question Submittal Form that is provided on the SCDOT Design-Build
website under the SCDOT Design-Build Standard Forms page.
https://www.scdot.org/business/design-build.aspx.
The intent of SCDOT is to maintain confidentiality of the one-on-one meetings.
However, SCDOT reserves the right to disclose to all Proposers any issues raised during
the one-on-on meetings, except to the extent that SCDOT determines, in its sole
discretion, such disclosure would reveal confidential or proprietary information.
3.7 Preliminary Alternative Technical Concepts
An ATC is a confidential request by a Proposer to modify a contract requirement,
specifically for that Proposer, prior to the Proposal due date. Requests for contract
modifications that may qualify as ATC’s may include, but not be limited to, changes in
design criteria, changes in alignments or location of facilities, changes to review and
submittal processes, change in material or structure types, change in interchange type,
etc. The ATC process provides an opportunity for Proposals to promote innovation,
reduce project costs, reduce project duration, find the best solutions, and to maintain
flexibility in the procurement process. ATCs are evaluated by SCDOT within the
deadline set forth in the Milestone Schedule. In order to be approved, an ATC must be
deemed, in SCDOT’s sole discretion, to provide a Project that is equal or better in quality
or effect on an overall basis than the Project would be without the proposed ATC.
Concepts that simply delete or reduce scope, require or are premised upon an addition of
a separate SCDOT project (or expand the Project’s scope), lower performance
requirements, lower standards, or conflict with environmental commitments, are not
eligible for consideration as ATCs. SCDOT reserves the right, in its sole discretion, to
reject any ATC. No ATC shall be included in the Proposal unless approved by SCDOT
in writing prior to the SCDOT’s Final Determination for Formal ATCs date on the
Milestone Schedule.

Project ID P040119 SCDOT | Design-Build Project Page 8 of 44
Cross Island Parkway (US 278) Toll Conversion
Beaufort County, South Carolina
Submittal of Preliminary ATCs
Preliminary concepts are intended to be an informal inquiry by the Proposer to
explore a concept and a quick method by SCDOT to review and comment on
potential development of ATCs prior to investment of time and resources by the
Proposer. Preliminary concepts shall present a description, deviations, and a
range of costs (savings, additional costs), as further described in Section 3.8.1.
Other items identified in Section 3.8.1 can be provided, but are not required. The
amount of information provided shall be constrained to the boxes provided in the
Preliminary ATC Submittal Form, which may be downloaded from the SCDOT
Design-Build website under the SCDOT Design-Build “Standard Forms” page.
Each Preliminary ATC must be one concept. No multi-options concepts are
allowed, i.e. each option is a Preliminary ATC. SCDOT will allow one single
tabloid sized attachment (11” x 17”) for detailed drawings or sketches.
Submission of preliminary concepts does not change or extend the submission
deadline of Formal ATCs.
Proposers shall be limited to one package of preliminary concepts and the total
number of preliminary concepts shall not exceed 6. The proposer shall rank their
Preliminary ATCs in order of importance or priority on the Preliminary ATC
Submittal Form.
All Preliminary ATCs shall be submitted electronically by uploading to the 01
ATC folder in ProjectWise. Each Preliminary ATC Submittal Form and
supporting information shall be combined in one PDF file per ATC that will be
uploaded to ProjectWise individually. When uploading to ProjectWise, the
Proposer shall enter appropriate attributes for each document in the ProjectWise
Client upload wizard. The web version of ProjectWise does not support ATC
attribute uploads. The document will not upload without entering the required
attribute information.
https://www.scdot.org/business/design-build.aspx.
The Proposer shall submit Preliminary ATCs for review in accordance with the
Milestone Schedule. All Preliminary ATC information being exchanged between
Proposers and SCDOT shall occur only on the specific dates shown, unless
otherwise directed by the SCDOT POC.
Confidential Preliminary ATC Meeting
SCDOT may offer Confidential Preliminary ATC Meetings at the request of the
Proposers. Proposers shall request a meeting in writing (email is acceptable)
addressed to the SCDOT POC with a copy to the alternate POC by the date
specified in the Milestones Schedule. SCDOT will reserve one hour of meeting
time for each Proposer that requests a meeting, and SCDOT will give time of day
preference in the order that requests are received. The purpose of this meeting is
to provide an opportunity to confidentially discuss the preliminary ATCs and

Project ID P040119 SCDOT | Design-Build Project Page 9 of 44
Cross Island Parkway (US 278) Toll Conversion
Beaufort County, South Carolina
questions. Prior to the meeting, SCDOT will provide a tentative response on each
Preliminary ATC. SCDOT will identify those preliminary ATCs that require
additional information, which will have priority in the meeting. SCDOT may
answer questions at the meeting orally. Oral responses are for information only
and are not binding. Nothing discussed at this meeting shall change the
requirements in the RFP. Proposers may bring additional information to the
confidential meeting to support their preliminary ATC.
Responses to Preliminary ATCs
SCDOT will provide a response to the Proposer in accordance with the Milestone
Schedule. SCDOT responses will be “Favorable,” “Not Favorable,”
“Addendum,” or “Not an ATC.” If additional clarification is needed after the
Preliminary ATC Meeting, Proposers are responsible for sending the clarification
as soon as possible so that SCDOT has an opportunity to assess the concepts
before providing a response in accordance with the Milestone Schedule. A
favorable response by SCDOT in no way guarantees that the concept will become
an approved Formal ATC. The favorable response may be subject to conditions.
3.8 Formal Alternative Technical Concepts
Submittal of Formal ATCs
Each Formal ATC submittal shall include the following.
• Sequential number: Each ATC shall be numbered sequentially identifying
the submitting Proposer. No multi-option submissions are allowed. (i.e., each
option is itself an ATC)
• Description: A detailed description and schematic drawings of the
configuration of the ATC or other appropriate descriptive information
(including, if appropriate, specifications, construction tolerances, special
provisions, proposed bridge types, product details, and a traffic operational
analysis). Drawings shall clearly indicate what is specifically proposed for
this project. Samples/Examples from other projects may be used but specific
commitments shall be identified for this project (i.e. member sizes, material
requirements, etc. Specification and special provisions shall be supplied if the
ATC covers materials, products, etc. not commonly used by SCDOT and not
covered in the RFP package or references. Traffic analysis shall provide
adequate information to clearly demonstrate the impacts of the Proposal on the
Project and shall contain summaries where appropriate to aid in review.
• Usage: Locations where and an explanation of how the ATC would be used
on the Project.
• Deviations: Clearly identify the sections and page numbers in the RFP which
is deviated and requires submission of an ATC. Include an explanation of the
nature of the proposed deviation and a request for approval of such deviations
or a determination that the ATC is consistent with the requirements of the RFP.

Project ID P040119 SCDOT | Design-Build Project Page 10 of 44
Cross Island Parkway (US 278) Toll Conversion
Beaufort County, South Carolina
If consistent with the RFP, please provide the sections and page numbers in
the RFP which address the concept.
• Justification: Justify use of the ATC and why the deviations from the
requirements of the RFP should be allowed.
• Schedule: Proposed changes to the Project schedule if applicable. If early
delivery is proposed, Proposer shall clearly define any proposed liquidated
damages or effect to the Contract if the early date is not met.
• Impacts: Identify potential impacts on vehicular traffic, safety, community,
utilities, right of way, and the environment.
• History: A detailed description of other projects where the ATC has been used
under comparable circumstances, the success of such usage, and names and
telephone numbers of project owners that can confirm such statements.
• Risks: A description of added risks to SCDOT and other persons/entity
associated with implementing the ATC.
• Costs: An estimate of the impact of the ATC on the Proposal Price and the
ATC implementation costs to SCDOT, FHWA, Contractor, or other person
during construction, maintenance and operations.
• Quality: A description of how the ATC is equal or better in quality and
performance than the requirements of the RFP.
• Operations & Maintenance: Any changes in operation or maintenance
requirements associated with the ATC.
The technical response to each item outlined above shall be provided in the
Formal ATC Submittal Form, which can be downloaded from the SCDOT
Design-Build website under the SCDOT Design-Build Standard Forms section.
Text submissions shall be limited to the form and shall not be provided as
attachments. Only drawing details, plan sheets, charts, tables, graphs,
specifications, special provisions, manufacturer data sheets, and supporting
reports/analyses can be provided as an attachment to the Formal ATC Submittal
Form.
A maximum number of 4 formal ATCs may be submitted to SCDOT by the
Proposer for consideration.
All Formal ATCs shall be submitted electronically by uploading to the 01 ATC
folder in ProjectWise. Each Formal ATC Submittal Form and supporting
information shall be combined in one PDF file per ATC that will be uploaded to
ProjectWise. When uploading to ProjectWise, the Proposer shall enter
appropriate attributes for each document in the ProjectWise Client upload wizard.
The web version of ProjectWise does not support ATC attribute uploads. The
document will not upload without entering the required attribute information.
https://www.scdot.org/business/design-build.aspx.
The Proposer shall submit Formal ATCs in accordance with the Milestone
schedule. All information being exchanged between Proposers and SCDOT shall

Project ID P040119 SCDOT | Design-Build Project Page 11 of 44
Cross Island Parkway (US 278) Toll Conversion
Beaufort County, South Carolina
occur only on the specific dates shown, unless otherwise directed by the SCDOT
POC.
Review of Formal ATCs
Review of formal ATCs shall be in accordance with the information and
Milestone Schedule provided herein.
Initial Review: Upon completion of the initial review, SCDOT will make a
final determination in accordance with Section 3.8.3, request more
information, or provide a conditional response.
More Information Needed: SCDOT may submit written questions to the
Proposer as outlined in the Milestone Schedule, and/or request a one-on-one
meeting in order to better understand the details of the formal ATC. In
addition, for questions related to minor clarifications, SCDOT may submit
written questions to the Proposer anytime during the initial review or any
subsequent review. Proposers will then have the opportunity to resubmit
according to the Milestone Schedule.
One-on-One Meetings: Confidential One-on-One Formal ATC meeting(s)
may be scheduled to fully understand the details of any formal ATCs. These
meetings will be restricted to those persons involved in the review of the
formal ATC and limited to discussions of the Proposer’s formal ATC
approach and any outstanding confidential questions. The purpose of this
meeting is to discuss proposed changes, answer questions, and other relevant
issues. Oral responses are for information only and are not binding. Nothing
stated at any formal ATC meeting(s) will modify the RFP or Contract
Documents. SCDOT reserves the right to disclose to all Proposers any issues
raised during the ATC meeting(s) in an addendum. However, SCDOT will
not disclose any information pertaining to an individual Proposer’s ATCs or
other technical concepts to other Proposers.
Conditional Response by SCDOT: If the SCDOT states a formal ATC is not
approved in its present form, it may be reconsidered for approval upon
satisfaction, in SCDOT’s sole discretion, of certain identified conditions that
must be met or certain clarifications or modifications that must be made by
Proposer. The Proposer shall not have the right to incorporate this formal
ATC into the Proposal unless and until the formal ATC has been resubmitted
in accordance with the Milestone Schedule, with the conditions, clarification
and modifications satisfied, and SCDOT has made a final determination.
No Response from SCDOT: If the Proposer does not receive correspondence
from SCDOT in accordance with the Milestone Schedule, the formal ATC is
deemed rejected by SCDOT, unless written notification to extend this period
is given by SCDOT.

Project ID P040119 SCDOT | Design-Build Project Page 12 of 44
Cross Island Parkway (US 278) Toll Conversion
Beaufort County, South Carolina
Final Determination of SCDOT
SCDOT will make one of the following written determinations with respect to
each properly submitted ATC:
The ATC is approved.
The ATC is not approved.
The submittal does not qualify as an ATC but appears eligible to be included
in the Proposal without an ATC (i.e., the concept appears to conform to the
RFP and to be consistent with other contract requirements).
The ATC is deemed to ta

[... truncated ...]